Contract duration: 3 years
Partner: LTD Gio-2007
Project Scope:
- PE Pipe Laying 140 km
- Steel Pipe Transmission Line 21 km
- House Connections
Financier: KFW Bank Group, Germany and the Municipality of Batumi.
Contract duration: 3 years
Partner: LTD Gio-2007