Contract Duration: 1,5 years
Partner: AS_Inshaat-N LLC
Project Scope:
- Rehabilitation of 2X1000m3 concrete reservoirs
- PE Pipe laying 68 km
- Steel pipe transmission line 8 km
- Pumping station with related mechanical and electrical works
Contract Type: FIDIC RED BOOK 1999
Financier: Asian Development Bank (ADB) and LLC United Water Supply Company of Georgia (UWSCG)
Urban Service Improvement Investment Program – Tranche 4.